Design, Construction And Operations Of A New Advanced Wastewater Reclamation Plant And Renovations To An Existing Primary Treatment Plant
Start date
Closing date
Country
Barbados
Sector
Apparel, Textiles & Accessories
IDB Project
Barbados Climate Resilient South Coast Water Reclamation ProjectImportant Notice
This action will open an external link.
Description
The objectives of the consultancy are to: augment existing water supplies; diversify potable water sources; enhance water supply resiliency by increasing the availability of reclaimed water treated to international discharge standards and reduce water insecurity through aquifer recharge; and reduce the impact of untreated effluent on marine life and the environment.
The milestones for the procurement process are as follows.
1. Invitation to prequalify.
2. Prequalification evaluation and selection of prequalified bidders
3. Invitation to Bid for prequalified bidders.
4. Bid opening (Technical)
5. Evaluation of technical bids
6. Bid opening (Financial)
7. Combined evaluation (Technical & Financial)
8. Notification of Intention to Award and Standstill period
9. Negotiations with awarded bidder
10. Contract signature
For more information on the scope of services to be provided and key activities, click on the "Access the original publication" button where you will find the official tender announcement.